Cotswold Estate Biomass Boilers

Cotswold farm biomass

This Cotswold farm had a standard seven day turn around planned. They could give us three days clear between washing down and re-bedding, so we had to be well organised to complete the job within the time slot.

Geberit pipe goes up in broiler house

Geberit pipe goes up in broiler house

 

This installation is going to be fed by two powerhouses that are currently under construction at our workshop in Sparkford, Somerset. Once complete they will be transported to site in sections and erected on the reinforced concrete base provided by a local builder of the farmer’s choice.

We plan to revisit site at the next turnaround in seven weeks, at which time the Big Dutchman units will be fitted. Three of their heatmaster 40R units will go into each shed.

Heatmaster 40R