We received the deposit from our client last week, and work begins today on site to extend his sheds to incorporate the boilerhouses and fuel stores. These four individual 199kw wood chip boilers will actually run on myscanthus, as the client has an established supply that was planted several years ago on his arable side.
Four ETA Hack 200 boilers are now on order with delivery dates scheduled for early September. In the meantime work begins on the ‘plug’ containing all the working parts of the boilerhouse.
Pictures to follow.